63. The authorization holder must, at least 7 days before, notify the Minister of the start of the following work:
(1)  the mobilization to the site where the drilling rig will be located;
(2)  the start of the drilling;
(3)  the sealing of the stratigraphic survey.
Where the holder cannot comply with the start date, the holder must as soon as possible notify the Minister, in writing, indicating the reasons justifying the delay. The holder must also notify the Minister, in writing, of the new expected date for the start of the work if the date is expected within 7 days of the first notice of delay or of the holder’s intent not to proceed.
O.C. 1251-2018, s. 63.
In force: 2018-09-20
63. The authorization holder must, at least 7 days before, notify the Minister of the start of the following work:
(1)  the mobilization to the site where the drilling rig will be located;
(2)  the start of the drilling;
(3)  the sealing of the stratigraphic survey.
Where the holder cannot comply with the start date, the holder must as soon as possible notify the Minister, in writing, indicating the reasons justifying the delay. The holder must also notify the Minister, in writing, of the new expected date for the start of the work if the date is expected within 7 days of the first notice of delay or of the holder’s intent not to proceed.
O.C. 1251-2018, s. 63.